 Rehabilitation damaged section of the gutter

 Rehabilitation and construction of the damaged section of the gutter (size 6.0Х4.0m. 100m long.) On the territory of M. Nozadze Street in Tbilisi.
  • Customer: Tbilisi City Hall
  • Location of the object: Tbilisi
  • Scope of work: Gutter – size 6.0Х4.0m. 100m long.
  • Completion: 2015

Brief description: Before the start of the main works, a temporary road to the damaged road was arranged. The soil was treated with 400m3 by means of a mechanism.
The soil was also treated in the cannel – 1555 m3. With the help of the mechanism, the damaged reinforced concrete structures were removed,
the construction territory was cleaned of dirt and silt. The collector was drained, after the construction of the monolithic reinforced concrete drainage collector was carried out with water-resistant concrete – 605 m3, the outer walls of the collector were waterproofed with 250 m2. All the above-mentioned works were carried out by strict observance of safety procedures.
Summary: The sewage collector on the territory of M. Nozadze Street in Tbilisi has been restored and the facility has been commissioned