Brief description: The works started with the preparatory works. In order to determine the location of the communication, a test cut-out of wells was carried out at 40 points. Asphalt concrete surface was removed, soil was treated with a mechanism, and trenches were strengthened. 2000 m of reinforced concrete and 400 m of polyethylene pipes were laid. Reinforced concrete monolithic inspection wells 41 of different sizes are arranged. Reinforced concrete monolithic drainage and storm intake chambers are installed. The existing open-type gutter cannel was cleared. Asphalt laying works have been carried out. All the above-mentioned works were carried out by strict observance of safety procedures.
Summary: The work corrected the rain water flow. The facility has been commissioned